IRIS # CFHWY00029/Federal Project # 0A15032

Glenn Highway: Parks to Old Glenn Pathway


This pathway will construct a 10-foot wide separated pathway along the north side of the Glenn Highway starting at the Matanuska Lake State Recreation Area and extending into Palmer.

The project is planned to be split into two phases due to limitations of project funding and design challenges. The phases are listed below and shown on the following map:

  • Phase 1 – The pathway between South Inner Springer Loop to West Arctic Avenue is complete.
  • Phase 2 – Project is bidding in April 2023; a contractor will be selected soon, and construction will begin in summer 2023. Construction is scheduled to be complete September 2025.

Project Map